Logan Motorway East-Bound Pavement Rehabilitation
SectorTransport, Urban
ClientDepartment of Transport and Main Roads
LocationLogan Motorway
DurationAugust 2019 – February 2020
Contract Value$6.4M

Transurban invited McIlwain to tender for the 62-day program of works which comprised drainage and crossover works during week nights; three weekend full eastbound closures for pavement rehabilitation, and an additional weekend eastbound full closure for overlay and guardrail works.

 

PROJECT OVERVIEW

2,700m3 of detailed excavation of median drain
1,200m of concrete vee-drain
6,500 tonne of asphalt
1,300m of guardrail replacement

 

The project was staged in three main areas.
Crossover area – including the provisional temporary crossover works
Full pavement rehabilitation
Area of median earthworks and vee-drain only.

 

Crossover(s) were completed first to facilitate contraflows for the full pavement rehabilitation works. The excavation of the median vee-drain and installation of the subsoil drains was undertaken concurrently to provide drainage to the subgrade prior to the excavation of the full pavement depth.
Pavement rehabilitation works were programmed to be completed over four, weekend shutdowns with traffic contra-flowed onto one lane of the westbound carriageway.
<
>

Transport

We pride ourselves on delivering optimal transport infrastructure throughout Queensland and NSW.

READ MORE

Building

McIlwain provide high-quality solutions that are designed to be both cost-effective and fit for purpose.

READ MORE

Urban

Working collaboratively with consultants, developers and councils to deliver urban infrastructure.

READ MORE

FEATURE PROJECT

Coomera Connector Stage 1 Central

Sector
Transport, Urban

Client
Department of Transport and Main Roads

Location
Helensvale to Molendinar

READ MORE

Search Projects

Region

Project Status


Sector/s

Mount Victoria Slope Remediation

Oakey Roads and Carpark Resurfacing

Hampton Downslope Remediation

Coomera Connector Stage 1 Central

Rockhampton Bruce Highway Intersection Upgrade

Cunninghams Gap Reconstruction Project

Burleigh to Palm Beach Motorway Upgrade

Deodar Drive Stormwater Upgrades

South Coast Region Natural Disaster Program

Beechmont Road (South Coast Natural Disaster Program)

Tully Timber Bridge Replacement

D’Aguilar Highway Wide Centreline Treatment

LOAD MORE