SectorTransport, Urban
ClientDepartment of Transport and Main Roads
LocationLogan Motorway
DurationAugust 2019 – February 2020
Contract Value$6.4M
Transurban invited McIlwain to tender for the 62-day program of works which comprised drainage and crossover works during week nights; three weekend full eastbound closures for pavement rehabilitation, and an additional weekend eastbound full closure for overlay and guardrail works.
PROJECT OVERVIEW
2,700m3 of detailed excavation of median drain
1,200m of concrete vee-drain
6,500 tonne of asphalt
1,300m of guardrail replacement
The project was staged in three main areas.
Crossover area – including the provisional temporary crossover works
Full pavement rehabilitation
Area of median earthworks and vee-drain only.